
The Zirakpur Panchkula Bypass was planned as one of the region’s most important road infrastructure upgrades, designed to ease congestion, reduce travel time and divert heavy traffic away from densely populated stretch points. But despite its significance the project has hit multiple roadblocks, pushing timelines further and leaving commuters confused about its future.
This crucial 19.2 km infrastructure upgrade which includes a 6.195 km elevated section was approved with a substantial Project Cost of ₹1,878.31 Crore . A major contributing factor to the delays and complexity is the substantial 17.57 hectares of forest land required for its completion. This has been a significant hurdle for residents of Zirakpur, Panchkula, and the wider Tricity region.
One of the biggest reasons behind the slowdown is the pending environmental clearance . Large scale infrastructure projects require approvals under environmental regulations especially when they involve land use change, cutting of trees or modification of natural drainage paths.In the case of this bypass the proposal needed multiple layers of assessment from environmental experts, local committees and state level authorities.
Crucial progress has been made on necessary environmental approvals with Stage - 1 Forest Clearance secured on July 31 2025 . However the project's ability to proceed remains restricted as Stage 2 Forest Approval is Still Pending .
Until these approvals are fully granted no major construction activity can move forward pushing the timeline back significantly and Land Acquisition Status has Completed in 2020.
The project has also undergone multiple alignment reviews due to concerns raised by different agencies:
Each department involved has its own inspection cycle and approval mechanism. Even a minor revision means documents must be re submitted and re evaluated.
Because the bypass connects two major administrative regions Zirakpur (Punjab side) and Panchkula (Haryana side) coordination between the two states becomes crucial.
However officials from both sides have confirmed that inter department approvals have taken longer than expectet especially for:
Such cross border projects often take more time due to additional paperwork and interstate communication.
Before any major excavation or construction begins utilities such as poles, transformers, sewer lines and underground cables must be relocated.
In this bypass’s case utility shifting has been slower than planned mainly because:
For daily commuters between Zirakpur and Panchkula the delay means:
Officials have stated that once clearances are finalized the project can move ahead at a faster pace. With the foundation work already prepared on some stretches the bypass could regain momentum quickly but only after all approvals are in place.
The procurement and construction timeline for the Zirakpur Panchkula Bypass has been adjusted with the Bid Deadline now Extended to December 20 . Following the bidding process the project is moving towards the contract phase with the Likely Work anticipated in Early 2026 . If this schedule holds the Tentative Construction Start is projected for March April 2026 aiming for an Estimated Completion date in 2028 . This timeline provides a clearer, though delayed, outlook for residents and commuters awaiting the completion of this critical bypass.
Shaheed Bhagat Singh Airport Mohali’s upcoming 8.5 km airport road is nearing completion and will open by year end, promising faster access, less traffic and a seamless travel experience for daily commuters and airport flyers.
Panchkula launches drone based land surveys, bringing unmatched accuracy, faster mapping and fully digitised urban records. A bold step toward transparent, modern and tech driven city planning.This initiative marks the beginning of the NAKSHA Urban Land Survey Programme